Bermuda Drainage Improvements

  • Project typeDrainage Improvements
  • Project valueDesign - $100,000, Construction - $900,000
  • Project scheduleConstruction anticipated to begin in Summer 2025

Project Description: This project aims to improve the drainage system along the back property line for Bermuda Estates lots 82 through 87 which includes utility relocation work for the installation of a closed drainage system with inlets and stormwater pipes to address the flooding conditions in the area. 

 

What's next?

  • Begin construction in Summer 2025.
  • Construction duration is estimated to be 6 months. 

Phase 1: Utility Relocation 

Phase 2: Drainage Improvements